Section B – Entering into a Relevant Contract – Treatment of Payments Under a Relevant Contract
Questions frequently arise as to whether a service or supply detailed on an invoice/document is subject to RCT and/or the VAT Reverse Charge. In considering whether a payment is subject to RCT, the contract under which the payment is being made must be examined to determine if it is a relevant contract. If it is a relevant contract, then all payments under that contract must be subjected to RCT. In considering whether the VAT Reverse Charge should apply to a payment, the service/supply on the invoice/document must be examined to determine if it is a construction
operation. If it is not a construction operation, then normal VAT rules apply and the payment is not subject to the VAT Reverse Charge. In practice, the decision on most contracts/payments will be clear cut and the operation of RCT and VAT will be straightforward. Issues are most likely to arise in the case of mixed contracts (repair and maintenance contracts for example See B11).
Department of Finance Circular 43/2006, as revised, sets out the procedures to be followed in respect to the award of public sector contracts. In brief, in the case of all public service contracts of a value of €10,000 (inclusive of VAT) or more within any 12 month period, the subcontractor will be required to produce either a valid tax clearance certificate or demonstrate a satisfactory level of subcontractor tax compliance. (The subcontractor can demonstrate a satisfactory level of subcontractor tax compliance by producing a Subcontractor’s Notification of Rate Determination showing a rate determined by Revenue of 0% or 20 %.) Any queries on the operation of Circular 43/2006, as revised, should be directed to the Department of Finance.
Note that irrespective of whether the subcontractor has a tax clearance certificate or not, the Board must operate RCT,and VAT where appropriate, on sums paid under relevant contracts.
Generally the main contractor is responsible for ensuring that the correct procedures are followed in relation to payments made to subcontractors engaged by them, unless there are special arrangements in the contract awarded to the main contractor. Department of Finance Circular 43/2006 contains some provisions in this regard.
Principal contractors are required to notify each contract separately unless the contracts are considered to be part of an ongoing contract with the subcontractor (see next question).
Strictly each contract must be notified to Revenue. However Revenue is aware that many principal contractors are in ongoing or rolling contracts with subcontractors. In schools, these would mainly be maintenance and repair contracts but could include other relevant operations.
Multiple, ongoing or rolling contracts:
Where there is an on-going contractual relationship (also known as a rolling contract) between a principal contractor and a subcontractor, a single contract notification will normally suffice. This includes situations where the jobs do not succeed each other immediately. The conditions are that
• The terms of the contract do not change;
• The parties to the contract do not change; and
• The subcontractor does not have to compete for the work (i.e. submit a new
tender for each contract).
This treatment is covered in more detail in Questions 9 and 10 of the FAQs (Principal Contractors)
In general a new site and a subsequent new SIN should be created for each overall Project. Within this there are possibilities where multiple SINs would exist for the same contract locations – this would occur where those contracts are not related to the same Project. Further information and examples are available here.
The subcontractor must provide the school with their name and tax reference number. Other information that the school must supply to Revenue will be available from the contract. Where the subcontractor does not provide a tax reference number further information will be required. Full details are available at www.revenue.ie/en/tax/rct/contract-notification.pdf
There is an onus on the principal contractor to establish the identity of the subcontractor who is party to the contract under RCT legislation. This should be a priority for the school in any case, to satisfy a range of Insurance, Health & Safety and Department of Finance requirements. The Income Tax and Corporation Tax (Relevant Contracts Tax) Regulations 2012 require a principal contractor to be satisfied as to the identity of the subcontractor. They also oblige a principal contractor to request documentary evidence of identity and to make and retain a copy of the documentary evidence provided, or record and retain relevant details from the documentary evidence given. There are, therefore, two requirements:
To be satisfied as to the identity of the subcontractor
To record the check carried out
A board should establish the identity of any subcontractor before awarding a relevant contract. Where there are ongoing contracts, all parties will be well known to each other and there is no issue. However, the principal will need to check documentary evidence. In the normal course of business, subcontractors will have to provide the board with details such as insurance cover, health and safety compliance, VAT document/invoice etc. and this will normally suffice.
In looking at specific items on an invoice/document it is important to remember that RCT should be operated where there is a relevant contract between a principal contractor and a subcontractor to carry out relevant operations. If any part of a contract is a relevant operation then all payments under the contract are within the scope of RCT. It is essential then that the detail of the contract is considered rather than merely looking at each individual invoice/document.
In general, the RCT treatment of the construction of new buildings or structures is straightforward and clear cut. Where a contract is for “supply and fit”, and the fitting is a construction operation, then RCT will apply to all payments under that contract.
Fixtures are goods, which have become attached to buildings in such a way that they cannot be removed without substantial damage being caused to the goods themselves or to the building to which they are attached. As distinct from fixtures, fittings are goods, which, though often attached to buildings, can be removed without substantial damage being caused to the goods themselves or to the building to which they are attached. Fixtures do not include carpets and other floor coverings (other than floor covering stuck down over its entire surface), cookers, hobs, gas and electric fires.
Repair: Repair is generally considered to be an operation carried out to fix, mend or restore the building/structure to its previous condition. Examples of repair include the replacement of constituent parts e.g. replacement of glass in a broken window, replace/fix broken tiles, mending faulty boiler. The repair of a building or structure is considered to be a construction operation, and therefore subject to RCT. Repairing removable machinery such as computers is not subject to RCT.
Maintenance: Maintenance is generally considered to be work carried out to keep the building, structure or associated lands, driveways etc. in proper or good condition. A maintenance contract is not within the remit of RCT. Routine cleaning is considered to be maintenance and is not subject to RCT. Maintenance includes operations such as cleaning gutters, roofs, carpets etc. and routine painting (other than painting of a newly constructed building).
However, if the contract is for maintenance and repair, then it is subject to RCT (where the repair related to a building, structure or system).
Repair and Maintenance contracts: If the contract provides for a single consideration for the repair and maintenance then RCT should apply to the full consideration, whether or not repairs are actually carried out. If the contract provides that a separate charge should apply where repairs are necessary then only the consideration applicable to the repairs is subject to RCT. Each case should be examined on its own merit.
Alteration and Repairs
Many questions arise in relation to the meaning of alteration and repairs. The phrase “alteration and repairs” is used in the legislation in four instances:
– Buildings and structures
– Works forming or to form part of the land
The repair of a building, structure, works forming part of the land or any works that have become part of the fabric of the building is considered to be a construction operation, and is therefore subject to RCT.
To be considered an alteration, there must be an element of materiality to the change in the building or structure. What is material? While the example given in the main body of the document says that replacing all windows is a material alteration, it does not say that RCT only applies where all the windows are replaced. The alteration must be significant. In most cases it will be obvious if the work is material or not. In a small school, replacing all of the windows in a single classroom might be material. In a large school it might not. There is a judgement call to be
made and, once it is made in a reasonable manner, Revenue will accept that the decision to operate RCT or not was made in good faith. Your local tax office will be able to provide guidance on any specific issues.
– Systems of heating, lighting, air-conditioning, soundproofing, ventilation, power supply, drainage, sanitation,water supply, or burglar or fire protection.
– Systems of telecommunications
Repairs to systems are within the scope of the RCT legislation. However, many repairs to systems are carried out under maintenance contracts. While maintenance only contracts are outside of the scope of RCT, many contracts that are referred to as maintenance contracts for “systems” also include an element of repair. Where there is any element of repair, for example in servicing contracts, all payments under the contract are liable for RCT. It is important to remember that it is the contract itself that is the defining factor, not the individual invoices/documents
issued under the contract. Again, to be considered an alteration to a system, there must be an element of materiality to the change in the system. “Add-ons” to existing systems are
not alterations and are therefore outside the scope of RCT.
In relation to telecommunications, this is an evolving area. The installation of a single, stand alone PC is not considered to be the installation of a system of telecommunications. The supply of hardware/software, or an add-on to an existing system, is not within the scope of RCT.
Again it is important to examine the contract, rather than individual invoices/documents. Where the term invoice is used this should be taken as referring to an invoice or document depending on the circumstances. The following examples relate to whether RCT applies to the contracts or not. The question as to whether the VAT Reverse Charge applies is set out in Section B11.
Click here for a table of examples Revenue has prepared.
As set out in B1, where any part of a contract is for relevant operations then the contract as a whole is a relevant contract and all payments under that contract are liable for RCT. The VAT Reverse Charge, however, only applies to payments that are in respect of construction operations, excluding haulage for hire. Again, it is essential then that the contract is considered rather than merely looking at each individual invoice/document and this is an important principle that Boards need to consider when operating the RCT and VAT systems.
A Board engages a subcontractor to build and fit out a gym under a single contract
Construction costs – €500,000 (VAT exclusive)
Fitting out of gym – €100,000 (VAT exclusive)
Relevant Contract Tax
RCT applies to all of the payments under the contract. For RCT purposes, the Board must notify the total payment to Revenue i.e. the VAT exclusive payment for the construction PLUS the VAT inclusive payment for the fittings. Assuming for the purposes of the example that only one payment is made to the subcontractor, the Board will make payment Notification as follows:
Construction Service (VAT exclusive) €500,000
Other service (VAT inclusive) €123,000
Total payment notification €623,000
If the subcontractor is at 20%, the RCT liability will be €124,600. The Subcontractor will be paid €498,400 (€623,000 less €124,600) and the total RCT due to be paid to Revenue by the Board is €124,600.
Value Added Tax
The VAT Reverse Charge can only apply to the construction element i.e. the construction of the gym. The subcontractor, therefore, must issue two VAT invoices/documents:
▪ A document for the cost of the construction of the gym on which the VAT Reverse applies i.e. a Vat reverse charge invoice for €500,000. The Board is accountable for VAT at 13.5%. The document will contain the legend “VAT ON THIS SUPPLY TO BE ACCOUNTED FOR BY THE PRINCIPAL CONTRACTOR”.
▪ A VAT invoice for the cost of the gym fittings that includes VAT at the 23% rate i.e. a VAT invoice for €100,000 plus VAT at 23%. (Not a construction service). The Board must pay the subcontractor the total invoice value of €123,000. For VAT purposes, only the VAT Reverse Charged amount (for the construction) should be returned by the Board. The Board are not entitled to claim a VAT input for the VAT suffered at 23% on the fittings. Board will account for RCT and VAT as follows:
VAT on Construction Service €500,000 @ 13.5% is €67,500
(T1 in VAT return) No credit can be claimed for VAT incurred on gym fittings.
Where the VAT Reverse Charge applies, RCT is charged on the VAT exclusive amount. Where the payment is subject to normal VAT rules (i.e. is not in respect of construction services) RCT is charged on the VAT inclusive amount.